The 6 published figures for Aluminium span a factor of 1.36 — the highest is 36% above the lowest. All are competently produced; none is a mistake. They come from 6 geographies, and a material's footprint follows the grid and the process mix of the place it was made as much as the material itself. They are characterised under 5 methods (EF 3.1, Base Carbone, IPCC 2021, TRACI 2.2, DESNZ), which is enough on its own to move a figure without anything physical changing. System boundary is usually the largest term: a figure quoted at the granulate stage and one quoted after forming answer different questions, and the row labels below say which each one is.

Lowest published
7.72
Highest published
10.5
Libraries
6
kg CO₂e per kg
A published range, not an uncertainty band — and deliberately no average.
kg CO₂e/kgLibraryMethodWhat the source calls it
7.72Europe — construction and building products
Ökobaudat (BMWSB)
EF 3.1Aluminium
declarations span 4.82–10.5 over 38
Median across real product declarations, module A1-A3 only. Recycled content is apportioned by the Circular Footprint Formula.
7.8France
ADEME Base Carbone® 2026
Base CarboneNew aluminium · manufacture · new
Carbon-neutrality basis: biogenic CO₂ is reported separately and held out of this figure. ADEME did not rate this factor's data quality. ADEME states an uncertainty of ±30%.
8.91Switzerland and Europe — BAFU
BAFU:2026 v1 (Swiss Federal Office for the Environment)
IPCC 2021Aluminium, primary, at plant
BAFU states the dataset covers: Includes raw materials and chemicals and disposal of residues. Primary production route, RER geography. IPCC 2021 GWP100; the same dataset on EF 3.1 is 8.91 kg CO2e/kg, which is a different characterisation model and must not be added to this figure. Database of the Swiss Federal Administration, BAFU:2026, Federal Office for the Environment, 2026.
8.94United States
USLCI (Federal LCA Commons)
TRACI 2.2Primary aluminium ingot
Aggregated cradle-to-gate, characterised with TRACI 2.2. 353 of its 583 flow references have no TRACI factor — water and land use among them — so this figure covers global warming and not those categories.
9.11United Kingdom
DESNZ GHG Conversion Factors 2026
DESNZaluminium cans and foil (excl. forming) — primary
Published combustion and material figures. For energy this product adds the well-to-tank terms the published set reports separately.
10.5Europe — Environmental Footprint node
European Commission EF node
EF 3.1Aluminium ingot, primary and secondary mix
The Circular Footprint Formula mix, which is the reference for any PEF claim about aluminium. Characterised with EF 3.1; 479 of 1005 flow references have no climate factor, mostly water flows that belong to other indicators.

Which one should you use?

The one whose geography and system boundary match your question — not the lowest, and not an average of them. If your supplier is in Europe, a UK or Australian figure is describing a different grid and a different process mix. If your bill of materials is granulate, a figure quoted after forming is counting a step you have not paid for yet. The prototype picks one and names which.

Attribution

  • Source: ADEME, Base Carbone®, Licence Ouverte / Open Licence 2.0.
  • Database of the Swiss Federal Administration, BAFU:2026, Federal Office for the Environment, 2026
  • Contains public sector information licensed under the Open Government Licence v3.0.

Reproduced for reference under the terms of the respective licences. Not offered for resale.

Use this

Picking the right Aluminium figure is only half of a footprint — the other half is how much of it your product contains. To put the two together, run a bill of materials containing Aluminium through the free carbon calculator — no sign-up, and it runs in your browser. For the whole picture, including the process and its scrap, model the whole route in the prototype, or see what TrueGauge does for a manufacturer.

Early access

Request early access.

Both products are pre-launch. We're working with an early group of manufacturers, architects, builders and sustainability teams to shape what gets built first — tell us which platform is relevant to you.

  • Shape the roadmap

    Tell us which decisions you need supported, and what the data has to do to be usable.

  • First access

    Be first in line as each platform opens to early users.

  • A direct line to the team

    Early conversations happen with the people building it, not a sales funnel.

Register interest

Which platform? *

This registers interest in early access — both platforms are pre-launch, so this isn't a product signup or a purchase.